The safety inspection included a review of the terminal’s design, construction, equipment, operations, maintenance, personnel training and firefighting systems. Cameron LNG also submitted its Marine Operations Manual and Emergency Manual to the Coast Guard for examination.

The project is nearing its first LNG cargo export after obtaining approval from the U.S. Department of Energy (DOE) to export up to 14.95 Mtpa to Free Trade Agreement (FTA) countries and non-FTA countries. In April 2014, the Federal Energy Regulatory Commission (FERC) issued the final environmental impact statement to construct and operate the liquefaction facility. FERC authorized the project in June 2014.